Project Manager for the decommissioning of the existing hydrant fuel system and
terminating the PANYNJ’s three fuel distribution mains with pipe caps and three
vents in vent pits. All previously decommissioned hydrant fuel piping and existing
hydrant fuel system piping to be decommissioned were located and the condition
verified for decommissioning via the slurry fill method. All decommissioned
piping lengths were recorded for modifying the Terminal 2 NY State MOSF Permit.
Project Manager/Engineer of Record for the decommissioning of the existing Terminal
3 hydrant fuel system. All decommissioned piping lengths were recorded for modifying
the Terminal 4 NY State MOSF Permit. Existing PANYNJ fuel distribution mains were
extended and terminated with isolation valves in pits. These mains were extended
and joined together on the Terminal 3 side of the valve pits to create a single
12-inch fuel main to service three new hardstands. A valve vault at the end of the
12-inch fuel main was designed to provide for the extension of the fuel main.
Hydrant pits and other fuel pits were provided along the fuel main. Full time Resident
Engineering and Construction Administration services were provided during the
construction phase work.
Project Manager/Engineer of Record for the Phase 1 extension of Concourse B’s hydrant
fuel system after the previous Project Manager left Argus Consulting, Inc. during
the construction phase of the project. Full time Resident Engineering and Construction
Administration services were provided during the construction phase work.
Project Manager/Engineer of Record for the Phase 2 extension of Concourse B to provide
regional aircraft contact gates. The design of the hydrant fuel piping extending from
the Phase 1 hydrant fuel system piping was developed with the fuel piping being routed
closer than normal to the terminal building and more than 100 feet away from the
building face to reduce the construction cost. The hydrant fuel system piping included
hydrant pits, low point drain and high point vent pits, a cathodic protection system
for the hydrant fuel piping and an emergency fuel shut off (EFSO) system. Full time
Resident Engineering and Construction Administration services were provided during
the construction phase work.
Project Manager/Engineer for a 30 percent design of a hydrant fuel system for a 15-gate
extension of Terminal 4’s Concourse A. The critical design issue is the ability to adjust
the route of the two existing Terminal 4 fuel mains to the Terminal 5 side aircraft
contact gates and the three Terminal 5 fuel mains passing Concourse A. The concourse
extension will include a drive through near the end of the existing Concourse A.
PANYNJ and other rules require that piping passing under buildings must be encased
in a pipe sleeve with sealed ends. The 30 percent design developed a plan to achieve
PANYNJ approval.